Q.31 | To produce a component, any of the four processes can be adopted. Process A: Fixed cost = Rs. 20, Variable cost/piece = Rs. 4 Which of the following process is the most economical to produce 100 pieces in a batch? | |
Ans | 1. Process B | |
2. Process D | ||
3. Process C | ||
4. Process A |
Correct Ans: 2