| Q.77 | The addition time in which non-critical activity can consume without increasing the project duration and known as: Where, EFT – Earliest finish Time, EFT – Earliest finish time, LFT – Latest finish Time, LST – Latest start time | |
| Ans | 1. Total Float = (LST + EST) or (LFT – EFT) | |
| 2. Total Float = (LST – EST) or (LFT – EFT) | ||
| 3. Total Float = (LST – EST) or (LFT + EFT) | ||
| 4. Total Float = (LST – EST) + (LFT – EFT) |
Correct Ans Provided: 2