| Q.30 | Which of the following is NOT a step included in pre-tender? | |
| Ans | A. Examining drawings and specifications to identify various items of work. | |
| B. Estimating the quantities of different items of work. | ||
| C. Evaluating the alternate methods of construction which is already identified. | ||
| D. Preparing tentative construction schedule with reference to stipulated time of completion. |
Correct Ans Provided: C