| Q.18 | Consider the given statements with respect to PERT and CPM methods and select the correct answer. Statement A : CPM was developed for planning, scheduling and control of civil works. Statement B : The event-oriented networks using three time estimates for activity durations having uncertainties can be termed as a PERT network. | |
| Ans | 1. Statement A is correct, but B is incorrect | |
| 2. Both statements are correct | ||
| 3. Both statements are incorrect | ||
| 4. Statement B is correct, but A is incorrect |
Correct Ans Provided: 2