| Q.14 | The type of estimate to cover additional works necessary for the development of project which was not considered in the original estimate, while work is in progress is : | |
| Ans | A. Supplementary estimate | |
| B. Revised estimate | ||
| C. Unit rate estimate | ||
| D. Complete estimate |
Correct Ans Provided: A