| Q.7 | P and Q together can complete (2/5) part of a work in 24 days. If P is thrice as efficient as Q, then in how many days Q alone can complete the same work? | |
| Ans | 1. 120 days | |
| 2. 240 days | ||
| 3. 180 days | ||
| 4. 150 days |
Correct Ans Provided: 2