| Q.21 | A can do a work in 8 days working 10 hours a day. B can do the same work in 10 days working 7 hours a day. How many days will they take to complete the work if they work together for 8 hours a day? | |
| Ans | 1. 4 | |
2. ![]() | ||
3. ![]() | ||
4. ![]() |
Correct Ans Provided: 2